day one hundred two // twenty eight.
today was HOPEFULLY the last day of wiring! robert told us this morning that the framing inspection is scheduled for thursday, so all the other inspections have to be done before then. and in order for the electrical to be inspected, the electrician has to have 2 days or so to connect everything to the breaker boxes. therefore, we had to get all our stuff done by today. fortunately, we didn't have much left to do! we had a team working on the exterior lights & outlets, a few on the wiring for the air conditioner units, a few people organinzing the mechanical rooms, and the rest of us doing random things that have been forgotten or missed here and there. i had to leave at 12, but it seemed that everything was being taken care of! so hopefully when i get to site tomorrow, everything will be done! :)